BRIDGELAND HIGH SCHOOL

Competition Field:

Installed Sub-drainage & Enka Drain system along with Geomembrane Liner. Once all base & finish rock was installed & laser graded the field was ready for turf install.


Track & Field Events:

For the running track we installed the ACO slot drain followed by the inside and outside concrete curbs. Then filled in the track with a Flex Base and laser graded. This was topped by 3” of Asphalt, and once cured the Beynon BSS200 Track Surfacing & Striping. Fielder’s Choice formed and installed the concrete pads and runways for the field events along with the equipment that goes with.


Practice Fields (4):

After the irrigation was installed we put down root zone sand and laser graded in preparation for sod installation.


Baseball & Softball Fields:

Installed Irrigation & Drainage system. Formed skinned infield areas and supplied red infield clay, formed mound and home plate areas. Installed root zone and sod for all grass areas. Provided bases, rubbers & home plates as well as dugout equipment.

Client: Cypress Fairbanks Independent School District

Architect: IBI Architects

General Contractor: Gilbane Construction

Completion Date: May 2017